Blog

The Great Sanitation Saga: How Surrey’s Growing Pains Led to Underground Innovation

September 04, 2024

Imagine a city growing so fast that 28 new residents arrive daily. This is the reality facing the City of Surrey, British Columbia. Measuring over 300 km2 with a population of more than 600,000, it is the fastest-growing municipality in the province. So fast, in fact, that Surrey is on track to outpace Vancouver by 2040. With a growing population comes the need to grow and upgrade the existing infrastructure.

Enter “Guilford the Greatest,” an ambitious development that’s creating a great opportunity to upgrade and grow the capacity of Surrey’s aging sewer system. This 20-unit townhome development is just one of the many new developments in the area that will need to be serviced by upgraded and new municipal infrastructure. In this case, the challenge is to figure out where and how the new sanitary capacity should be built.

Initially, the developer pitched a new 350mm (14”) sewer main in a new alignment in the road along 148th Street. A main arterial, 148th Street, is already congested with underground services. Fearing months of traffic disruption to both residents and businesses, the City didn’t want to dig up the road and suggested their consultant contact PW Trenchless Construction Inc. to look at alternatives.

Known for their “groundbreaking” work, these trenchless technology specialists offered an innovative proposal to double the capacity of the existing pipe without digging up the road using pipe bursting technology. Picture a large high-tech bursting head burrowing through the old 200mm asbestos cement pipe, simultaneously splitting it and pulling a new 400mm HDPE pipe into place along the same alignment. All this happening 3 meters below the bustling street above, with only a few strategic excavations needed.

Challenges: Underground and Overhead

The prime contractor sole-sourced PW Trenchless to pipe burst the existing 200mm (8”) asbestos cement pipe and replace it with a 400mm (16”) HDPE pipe over a length of about 130m (425’) with minimal excavation.

Before the work could begin a sewer bypass was installed using 2 – 150mm (6”) hoses under pressure to contain the contents of the existing 200mm (8”) pipe. The 2nd hose was used as a standby bypass in case something went wrong. PW Trenchless also had to bypass one 200mm (8”) gravity sewer that intersected the existing main, which happened to be located along an easement that was not abandoned but had been forgotten about because it was hidden under vegetation on private property. The PW crews found the service connection and redirected the contents from the unexpected 200mm (8”) gravity sewer to the upstream end of the pipe bursting project so that the contents of the pipe was treated with the rest of the contents of the existing AC sewer.

Even though all the PW Trenchless work trucks have an M-Scope utility locating device, it was still necessary to retain a subsurface utility engineering (SUE) contractor because of the large number of services and the fact that the M-Scopes that are used cannot pick up the fiber optic cables.

There were three manholes along the existing alignment and several light standards, the sidewalks, a major driveway to a park, and hydro poles that had to be managed. Even though the project was a trenchless pipe bursting project, excavations are necessary at the entry and exit pits; these are usually located at existing manholes. The existing pipe was buried over 3m (10.5’) deep, so the excavations of the entry and exit pit were about 14m (45’) long. A third excavation was necessary to access the centre manhole. This centre manhole was initially going to be replaced; however, the contractor was able to jackhammer 2 – 1050mm (40”) holes into the sides of the existing middle manhole to accommodate the new HDPE pipe.  The excavation for the middle manhole was about 2 metres (6’) long and just over 3 metres (10’) deep.

Additionally, because the pipe size was being doubled, some heaving was expected, and a few of the lamp standard foundations had to be adjusted after the pipe bursting work was complete.

Another challenge along the alignment was the height of the communications conductors that were under-built on the BC hydro poles. The wires were only about 5.5 meters (18’) at the project’s north end. Threading the layout through all the obstacles, both below and above the ground, required careful placement and staging of the excavators supporting the HDPE pipe during the actual pipe pulling stage of the work.

The Results

For this project, the developer considered both open-cut and trenchless methods. In the end, the trenchless method proved not only less disruptive but also more cost-effective than traditional open-cut techniques. More importantly, the prime contractor liked handing it over to PW Trenchless, knowing there would be less restoration necessary with the sidewalks, hydro poles, and light standards.

The developer was also attracted to PW Trenchless because of their excellent relationship with the City of Surrey which led to smoother sailing through the inevitable hurdles of urban construction. There was also a high confidence that PW Trenchless would capably manage the sewer bypass, traffic control and all other construction-related issues – which they did. Offering a predictable lump sum to carry out and manage the work was the cherry on top.

As Surrey continues its impressive growth, the tale of “Guilford the Greatest” stands as a testament to the power of PW Trenchless’s innovation in solving the growing and aging pains of a booming city.

Design - Build

An alternate tendering process where the contract is awarded to one entity which comprises both engineering and contracting.

Because PW Trenchless Construction offers such innovative solutions for underground utilities, it is often beneficial for the owner to request solutions based on a performance specification. This allows PW Trenchess to offer unique solutions while working with equally innovative engineering companies. Learn more about design - build here!

More Info

New Installation

New installation methodologies include HDD & traditional open cut Learn more about new installation here!

More Info

Pipe Replacement & Rehabilitation

In this day & age of pipe systems reaching the end of their projected lifespan, pipe replacement and pipe rehabilitation have become major fields of engineering.

PW Trenchless Construction provides viable options such as pipe bursting, loose fit lining and internal pipe re-construction whether partial & fully circumferential. Learn more about pipe replacement & rehabilitation here!

More Info

Culvert Rehabilitation

The aging culverts under roads and highways in many case have reached the end of their engineered life-span. We consider the rehabilitation or replacement of these culverts to be vital to our built environment.

PW Trenchless has been a pioneer in working with MOTH, railway companies and municipalities in developing rehabilitation methodologies for the hundreds of thousands of culverts that currently exist in BC. We have offered solutions in both procurement and construction from design-build to sliplining, invert rehabilitation and full circumferential relining. Learn more about culvert rehabilitation here!

More Info

Point Repairs

Often pipe failure can be concentrated to one section, for various reason, leaving the rest of the pipe in good condition. The repair of these localized failures are know as external point repairs (EPR's).

EPR's demonstrate PW's ability to work as both a trenchless and civil contractor, completing EPR contracts using our civil contracting skills and assisting other pure trenchless contractors who only have the capacity to work in an existing pipe. Learn more about point repairs here!

More Info

Pipe Upsizing

Pipe upsizing is the fundamental concept of pipe bursting.

The vast majority of pipes are less than or equal to 200mm in diameter, but with today's densification practices of urban design, there is a major demand to increase current capacity to handle extra flow. Pipe bursting provides the ideal solution to this issue, particularly in an urban setting. Learn more about pipe upsizing here!

More Info

Horizontal Directional Drilling

Horizontal Directional Drilling is a low impact Trenchless construction service where pipe is installed in a shallow arc along a bore path which has been created by a drilling rig. Often the terms Horizontal Directional Drilling (HDD) and Directional Boring are used interchangeably, but in our industry we use the word “boring” when we utilize smaller sized drilling rigs with small diameters for short crossings in the hundreds of feet, and we use the word “drilling” when we utilize larger rigs with large diameters for long crossings in the thousands of feet. Learn more about horizontal directional drilling here!

More Info

Primus Lining

Primus Line® is a flexible sliplining solution for the trenchless rehabilitation of pressure pipes. The system consists of a flexible Kevlar® reinforced liner and specially developed end fittings. Primus Line® is not bonded to the host pipe and is self-supporting. An annulus remains between Primus Line® and the host pipe.

Developed by experienced engineers, the system is suitable for different media as well as various application needs and has already proven itself in numerous projects.Learn more about primus lining here!

More Info

Interested? Let’s Talk

  • This field is for validation purposes and should be left unchanged.

Clients We Serve

City of New Westminster logo
City of Delta logo
City of Surrey logo
City of Port Coquitlam logo
UBC logo
City of Coquitlam logo
City of Nanaimo logo
City of Pitt Meadows logo
City of Vancouver logo
BC Rail logo
City of Burnaby logo
City of Whistler logo
City of Victoria logo
City of Metro Vancouver logo
City of Squamish logo
City of West Vancouver logo
City of Richmond logo
City of Abbotsford
City of Chilliwack
Township of Esquimalt
City of Maple Ridge
City of North Vancouver
City of Port Moody
Regional District of North Okanagan
Town of Sidney
Ministry of Transportations and Infrastructure
District of Kent
Langley City
Township of Langley
White Rock

Join Our Team

When you join PWT, you become part of a community of people who are engaged in the most innovative practices in the Trenchless Industry. We have been instrumental in setting up a scientific method for cities to gain carbon offsets/credits from their use of trenchless construction. This system has been reviewed by the BC Government and has been approved as of December 2018. We expect to see it in common use shortly.

Stay At The Forefront Of Trenchless Technology

Subscribe to our newsletter for cutting-edge industry updates, expert knowledge, and exclusive content.

  • By clicking subscribe, you agree to receive emails from PW Trenchless and accept our Privacy Policy.

  • This field is for validation purposes and should be left unchanged.
Let's Talk